Project-Schedule & Delay-Notice AI Agent

A time bar usually bars: a notice missed by a day loses the entitlement on merits nobody reaches. Where a court may now relieve one, the evidence decides, and the agent keeps it.

4–6 weeksTypical delivery
Your stackDeployment
Drafts onlyPlanner review
Agent CareAfter launch

What this agent does

Computes the deadline; it does not serve the notice

In
01

Compute the notice-deadline register from the clocks and triggers your executed contract sets.

02

Diff each programme revision against the last — activity, duration, tie and calendar.

Reason
03

Archive every revision immutably, with its author, timestamp, data date and provenance.

04

Compute time elapsed on each open item and escalate long before the window closes.

05

Diff field progress against the model and flag as-built dates no record supports.

Decide
06

Diff the model against the accepted programme and flag drift instead of closing it.

07

Route every register item and every draft to the planner who holds it.

Out
08

Archive the records read, the draft, the amendments and the decision against the event.

09

Execute write actions only inside the approval boundaries agreed during implementation.

Product statement

The agent computes deadlines and drafts; the contracts administrator serves the notice — and a date that has passed cannot be un-passed by anyone.

Example workflow

One delay event, record to draft

AgentHuman
1Delay event recordedSite diary, progress update, instruction or correspondence
2Clocks resolvedThe notice periods, triggers and escalation steps configured from the contract as executed
3Register item computedDeadline, time elapsed and confidence
4Controls appliedConfigured-clock checks, evidence checks, escalation timers and confidence threshold
No human action required

Stages 1 to 4 run unaided, and nothing is served at any of them — the agent is computing deadlines, and the planner's lane opens at the confidence gate.

5DecisionBranches at the confidence threshold
High confidence

Goes to the planner who holds it.

Low confidence

Adds a contracts read first.

Planner review

The item is held with its deadline, the records behind it and the confidence.

Acknowledge · Amend draft · Send to contracts
Acknowledged — back with contracts
6Schedule systems updatedOnly where write access and approval policy allow it
7Outcome evaluatedEscalation lead time, drafts amended, notices served and events that ran past the window
Amendments

Every amendment made in review is counted in the evaluation.

What should not run autonomously

Human approval stays in control

Outside the boundary — human approval required8 items
Serving or transmitting any contractual notice.
Approving, rejecting or accepting a programme submission.
Changing the baseline, data date, calendars or logic.
Selecting the delay-analysis method.
Automation boundaryAgent acts unaided
Compute the notice-deadline register with escalation timers for each named owner.
Diff two programme revisions, activity by activity.
Reconcile field progress against the model.
Archive every revision with its author, timestamp and provenance.
Any write happens inside the boundaries agreed at implementation, and never into the live programme.
Characterising delay as excusable, compensable or concurrent.
Certifying, waiving or forecasting liquidated damages.
Declaring time at large, or a claim time-barred.
Releasing a schedule or forecast outside the project.

Example output

One register item, annotated

Everything the agent computes is attached to the records it was read from.

Register item · single delay eventIllustrative example
Package
Delay event
Window elapsed
Item state
Confidence
Clock source
Piling subcontract
Access to the piling zone withheld by the principal
52% elapsed
Escalated — draft with the planner
93%
The contract as executed
As receivedTaken from the site records and the clocks configured for this contract — nothing on this side is written by the agent.
What was read Site diary entry Accepted programme revision Correspondence log
Why this deadlineThe period comes from the contract as executed and amended.
ActionAcknowledgeAmend draftSend to contracts
What the score decidesBelow the configured threshold the item picks up a contracts read before the planner sees it.

Value

Where AI adds value

The same four claims, placed at the point in the workflow where each one applies.

Where the value landsValue 01 – 04
Every delay eventFrom records and the contract
03Deadline

Apply the contract as executed

Standard forms are almost always amended, so the agent works from the clocks configured for your contract, not the printed form.

01Approved path

See the bar before it closes

Routine register items and revision diffs arrive already computed.

02Human review

Send review to the tight clocks

Short windows and low-confidence items are marked, so the planner's read starts where the clock is tightest.

04Build an evidence trail

Every revision keeps its author, its timestamp and the diff that produced it.

Integrations

Typical integrations

Five system groups connect to the same agent. Which of them are in scope is decided in discovery.

CPM scheduling enginesOracle Primavera P6 · Asta Powerproject
Microsoft Project · Deltek Open Plan
Schedule analyticsDeltek Acumen Fuse · SmartPM
Revision exports and progress updates
Field progress captureProcore · Autodesk Construction Cloud
Site diaries and daily records

Agent

Project schedule & delay notices

Reads the records
Computes the deadlines
Holds for the planner

Contract and document backboneOracle Aconex · Trimble Viewpoint
Notice and contract registers
Observability & evaluationOpenTelemetry · Langfuse
Supported monitoring/evaluation sources

Integration availability depends on the client's existing systems and API access.

Agent controls

Six layers between the model and the notice

Each control wraps the one inside it. What a layer does not catch is named in the failure-mode map below it.

L6 · Outermost — last line of defenceInward → L1 · closest to the model
L6Rollback / safe modePull the agent back to register-only when evaluation or production signals degrade.Roll back
L5Version monitoringTrack model, prompt, calendar-default and contract-configuration changes.Track
L4TraceabilityRecord the revision read, the clock applied, the reviewer and the decision behind each item.Record
L3Planner reviewHold items for the named planner; it governs release, not whether the notice later served is right.Gate
L2Policy guardrailsTest items against the configured clocks and the write boundary; a failure returns the item.Restrict
L1Confidence thresholdsRoute low-confidence items to a contracts read before the planner sees them.Require review
Model coreItem produced — deadline, time elapsed, records gathered and confidence
L1 – L2Test whether an item may stand
L3Puts the decision in the planner's hands
L4 – L5Hold the revision history the claim rests on
L6Stops drafting when evaluation signals slip

How Nestack evaluates it

Evaluate the notice workflow — not only the finished programme.

Coverage runs the whole depth of the workflow, and every layer is cut by slice.

Surface — the deadline the project acts on
Depth of coverage ▼
E1Final-output evaluationWas the deadline computed from the clock this contract actually sets?
E2Step-level evaluationDid the agent read the right revision, records and contract configuration?
E3Tool evaluationDid it read and write the correct project and the correct register?
E4Confidence calibrationDo low-confidence items actually attract more planner amendments?
E5Slice evaluationHow does performance change across specific contract forms?
E6Business outcomeHow many events needed an amendment, or ran past the escalation window?
Floor — the entitlement the contractor keeps

Failure modes

Where each failure originates in the agent

Seven failure modes, plotted at the stage where each one begins.

Agent lifecycleDirection of processing →
01 · Retrieval1 mode
PJ-01

Unaccepted revision pulled

Analysis runs against a programme that was never the datum.

Stage gathersRevisions, site records, progress updates and configured clocks
02 · Reasoning2 modes
PJ-02

Float read as no delay

Float consumed by an employer risk event is reported as no impact.

PJ-03

Concurrency from overlap

Calendar overlap is read as concurrent delay to completion.

Stage proposesDeadline, time elapsed and confidence
03 · Tool / write2 modes
PJ-04

Live programme rewritten

A revised data date and re-levelled resources erase the as-planned logic.

PJ-05

Register item auto-closed

An item closes as no entitlement and the escalation clock stops.

Stage writesOnly where write access and approval policy allow it
04 · Output1 mode
PJ-06

Forecast reads as an admission

Client-facing wording concedes contractor culpability.

Stage returnsThe register the planner reads before serving
05 · Change / Version1 mode
PJ-07

Silent calendar change

A tool upgrade shifts retained logic, so the longest path moves.

Stage tracksModel, prompt, calendar defaults and contract config
Sev-1 · a held act performed by the agent Sev-2 · a wrong deadline reaches the planner Sev-3 · records degrade, item routes to review

Affected slices

A steady average can rest on one contract form

The all-event baseline is the number a monthly report shows; underneath it a small set of contract cohorts absorbs most of the late escalations. Nestack reports the rate by slice, not only in total.

Slice performance — reported separately, not only in aggregateIllustrative example
SliceFailure rateLift Lift vs. thresholdStatus
FIDIC and NEC EPC packages5.9%3.7× Review
AS 4000 head contracts4.0%2.5× Review
JCT and A201 traditional build2.4%1.5× Watch
Framework programmes0.8%0.5× Normal
Bar: late-escalation-rate lift vs. an all-event baseline · scale 0–4.0× · tick marks the 2.0× review threshold 2 of 4 slices over threshold

Evidence-linked improvement

Nothing closes until the suite grows

The loop shuts when the miss is a case in the suite, not when someone has explained it.

Improvement cycle · five stagesSwitchback — the path turns at Improve and returns at Learn
01Detect

Late-escalation rate rises in a contract-form slice.

02Diagnose

Not isolated until the archive, the records and the register agree on one cause.

03Improve

Whatever changes ships against a version, with the notices that prompted it attached.

04Verify

Nothing ships until the affected cases pass a second time.

05Learn

The suite grows by one case; so does the notice playbook.

Learn → DetectThe return edge. Detection next time runs against a longer suite.

Typical build scope

Twelve workstreams across six weeks

The build scope read against the delivery timeline. Week structure follows the six-week plan — discovery, sources, notice workflow, evaluation, integration, then production validation and handover.

Workstream Week 1Week 2Week 3Week 4Week 5Week 6
01Programme workflow discovery and boundary work.
02Schedule and field-record assessment.
03Contract-clock, calendar, float and notice-rule mapping.
04Programme ingestion and normalisation.
05Deadline computation and revision-diff logic.
06Confidence scoring and register-item routing.
07Planner review workflow.
08Scheduling and document-system integration.
09Notice-timing regression cases.
10Guardrails and service controls.
11Revision-archive instrumentation.
12Deployment, documentation and Agent Care handover.
12 workstreams · 6 weeks · bar shows the weeks a workstream is active — several run in parallel Final scope and sequence confirmed in discovery

Engagement tiers

What each tier includes

Rows are the capabilities named in each tier's scope. Higher tiers include everything below them.

Capability✓ in scope · — not at this tier PilotOne project, one contract form ProductionProduction scheduling systems AdvancedMultiple projects / forms
Introduced at Pilot
Deadlines from your executed contract
Planner review
Notice-timing baseline
Introduced at Production
Reporting by contract form
Review workflow in your systems
Approved write-back
Client and funder reporting feed
Introduced at Advanced
Multi-form portfolios
Multi-stage contract review
High event volume
Enterprise programme controls
Build price From $5,000 From $8,000 Custom quote
Final build priceConfirmed after discovery based on integrations, workflow complexity, event volume, approval controls and deployment requirements.
Separate from buildBuild pricing is separate from recurring Agent Care, which covers managed monitoring, evaluations, incidents and verified improvements after launch.

What we need from you

What you bring, and what we build with it

Each input maps to a piece of build scope and a week in the delivery timeline.

You bringWe build with it
01Your contract forms and their executed amendments Contract-clock and trigger mappingWeek 1
02Representative programme revisions Deadline baseline, revision diffing and progress reconciliationWeek 2
03Your notice register and escalation practice Escalation-timer mapping and automation-boundary definitionWeek 1
04Access to relevant APIs, feeds or exports Scheduling, field and document assessment, then integration setupWeek 2
05Delay events you did not notice in time Notice-timing cases and the evaluation suiteWeek 4
06Where a draft notice stops and waits for the planner Confidence scoring, item routing, guardrails and approval controlsWeek 3
07Named planners to review the register Planner review workflow, then pilot and production validationWeeks 5–6
Nothing else is required Deployment, documentation and Agent Care handover are ours.

Delivery timeline

Four phases across six weeks

Each phase is drawn across the weeks it truly occupies. Week 5 carries evaluation and pilot at once.

Phase W1W2W3W4W5W6
Discovery W1
Build W2 – W3
Evaluate W4 – W5
Pilot & Launch W5 – W6
Week focus W1Programme workflow discovery, clock mapping and the automation boundary W2Source integration and the deadline baseline W3Diff logic, confidence scoring and review controls W4Evaluation suite, guardrails and failure-mode testing W5Scheduling-system integration, pilot events and targeted corrections W6A full monthly programme cycle under the planner, then handover
Reading the bandEach bar covers the weeks its work is named in and no others. The week 5 overlap is real, not padding.
At the end of W6Once the cycle validates, Agent Care owns the running agent.
DurationSix-week plan shown · typical delivery 4–6 weeks depending on scope confirmed in discovery.

Next step · Construction AI agent

Build a project-schedule agent around your notice clocks.

Show us your contracts as executed, your programme revisions and who serves the notice. Once a window closes the entitlement closes with it, so we map the clocks first and name what the agent never touches.

Nestack Agents · Project schedule and delay noticesAGT-CN-03 · Agent Care available after launch